Rabat Sale Airport

1.  PROJECT’S OPPORTUNITY:  Terminal 1 refitting  

Current terminal 1 surface is 5 000 m² and its annual holding capacity is 700 000 passengers.

Terminal 2 which has been used for hadj and Omra flights has underwent refitting to allow simultaneous departure and arrival flights processing. Its annual holding capacity is 500.000 passengers and has to handle the overall air traffic until 2009 - date when the refitting of terminal 1will be completed.

 

2. PROJECT’S CONSISTENCY

  • Surface : 17 000 m²- 182 986,48ft²
  • Capacity for treatment : 2 Millions passengers/year
  • Overall costs : 200 MDhs
  • Starting : End of 2009

3. Each terminal's related surface area :

Operations area

Current Terminal 1 (m²)

Terminal 2 (m²)

Post-expending Terminal 1 (m²)

Public hall

915

700

2000

Booking area

230

400

1500

Boarding area

425

350

1150

Landing area

425

530

5620

Luggage claim area

775

625

1600